Outlet pipe construction and Wastewater Treatment Plant in Fontiveros (Ávila)

Outlet pipe construction and Wastewater Treatment Plant in Fontiveros (Ávila)

Implementation of a wastewater treatment plant by activated sludge method

Description of the Works:

Indepro performs the functions of Construction Management, verifying the correct execution of the work, according to the conditions defined in the project as well as in the specifications.

The design population is 1500 inhabitants obtaining a maximum daily volume of 750 m3.

Customer: Junta de Castilla y León

Allocation Date: 2011

Bidding amount with VAT: 1.291.516,68 €

Junta de Castilla y León

The work consists in the execution of a wastewater treatment plant by activated sludge method with main lines consisting in:

  • Water line: pretreatment with ladder screen, activated sludge biological treatment with compact reactor-decanter element.
  • Sludge line: sludge thickening by gravity and centrifugal dehydrator.