The project consists in the installation of a prefabricated prestressed concrete tank, as well as the installation of the connection pipes between the tank and the collector, the existing tank and the connection with the municipality. The tank will be of the SC-6 type, consisting of a set of HP-40 concrete panels assembled on a reinforced concrete slab.
Customer: Junta de Castilla y León. Consejería de Medio Ambiente
Allocation Date: March 2007
Termination Date: November 2008
Construction Budget: 146.703,43 €
The total volume of the tank is 253 m3, with a water level height of 4.5m. Next to the tank, the construction of a valves camera is planned, to accommodate the flow measurement and control elements, as well as the dispensing equipment.